Learning outcomes
The method
Nutzwertanalyse — weighted scoring — turns a decision between alternatives into something you can hand to somebody else and have them follow.
-
List the criteria that matter.
-
Give each a weight; the weights sum to 100.
-
Rate each alternative per criterion, on a fixed scale (say 0–10).
-
Multiply, sum, compare.
| Criterion | Weight | Idea A | A·w | Idea B | B·w |
|---|---|---|---|---|---|
Team can build it in one year |
30 |
8 |
240 |
5 |
150 |
Somebody actually needs it |
25 |
6 |
150 |
9 |
225 |
We learn something new |
20 |
7 |
140 |
8 |
160 |
Data protection is manageable |
15 |
9 |
135 |
4 |
60 |
Testable without a real client |
10 |
8 |
80 |
6 |
60 |
Sum |
100 |
745 |
655 |
The number is not the point. The visible reasoning is: anyone can now ask "why is feasibility weighted higher than novelty?" — and that is a question the team can answer, unlike "why did you pick A?".
Choosing criteria
A criterion is useful only if the alternatives differ on it. "Must be software" scores 10 for everything and contributes nothing but arithmetic.
| Weak criterion | Better criterion |
|---|---|
"Is interesting" |
"At least three of us want to work on it in February" |
"Modern technology" |
"Uses at most one technology none of us has used before" |
"Useful" |
"There is a named person who will use it and can be asked questions" |
Set the weights before you rate the alternatives. Otherwise the weights become the place where the preferred answer is engineered.
Reading the result
-
A clear gap — take the winner.
-
A gap of a few percent — the method says: these are equivalent. Then decide on something the table does not capture, and write down what that was.
-
A result that feels wrong — look for the criterion you left out. That feeling is usually information, not stubbornness.
Decisions
-
Every team documents its project choice as a weighted scoring table in the project proposal.
-
Criteria and weights are the team’s own. There is no prescribed catalogue — a borrowed catalogue produces borrowed decisions.
-
Weights are fixed before the ratings are entered.
-
If two alternatives end within a few percent of each other, the team writes one sentence saying what actually decided it.
Pitfalls
-
Tuning weights until the desired alternative wins. It happens, it is visible in the history, and it destroys the point of the exercise.
-
Criteria that do not discriminate. They add work and change nothing.
-
Too many criteria. Above roughly seven, each weight is so small that the sums are noise.
-
Treating the number as the decision. The table supports a decision; the team makes it.
Terminology
| Deutsch | English |
|---|---|
Nutzwertanalyse |
weighted scoring / utility analysis |
Kriterium |
criterion |
Gewichtung |
weight |
Bewertung |
rating |
nachvollziehbar |
traceable, comprehensible |
Further reading
-
PUMA 8/05, Nutzwertanalyse — the source used for this module
-
Module
governance-stakeholders-goals— turning the chosen idea into goals